Friday 12 July 2013

July 12th 2013 update
































Things are really moving forwards now.
  • The kitchen and utility rooms are essentially complete and tiled and awaiting vinyl flooring on Tuesday and appliances thereafter. 
  • Blinds are going in generally the week after. 
  • The studio is finished apart from some painting and blinds. 
  • The guest bedroom is finished apart from some painting and blinds. 
  • The garden room (Lis calls it the Jardinador) is finished just awaiting blinds. 
  • The little bedroom is awaiting fancy shelving and blinds.
  • Our main bedroom is almost complete with Sliderobes due to fit wardrobe Aug 9th. 
  • The en-suite structure (walls and ceiling) is in place as is the bath, but not the vanity unit, basin, toilet or tiles.  
  • Outside, the patio and path to it has been laid but not paths/driveway elsewhere.
  • All carpets ordered.
  • Curtains ordered for small bedroom and main bedroom.
  • Furniture ordered for hall and lounge
  • Fire surround marble should be ready next week.



No comments:

Post a Comment